The starting point
Record what is changing, its effect on price and timing, and the approval status before treating it as agreed extra work. Carry that reference through to billing.
Separate a request from an agreed change
Record the request against the original job, including who asked and what they want changed. Describe the difference from the existing scope. A note saying “extra work” leaves too much for the next person to infer.
Check whether the work is already included before pricing it again. If it is a correction to something you were already responsible for, that is a different situation from a newly requested addition. Resolve that distinction before preparing a revised amount.
Make the effect on price and timing visible
Illustrative example: the original scope is $1,000 and a requested addition is priced at $200. Once that addition is approved, the revised service amount is $1,200 before applicable tax. Record the original reference, the $200 change and the approval together.
If the addition needs another visit, different materials or a later completion date, record that too. The new price alone does not explain what the scheduler or crew should do. The downloadable record includes a blank worksheet and a filled example.
- Original job and scope reference
- Requested addition or omission
- Change in amount and revised total
- Effect on work, materials or timing
- Approval status and supporting reference
Give the crew an unambiguous instruction
Make it easy to tell whether a change is requested, awaiting an answer or approved. The person on site should not have to guess from an old message. If the request changes again, update the current instruction and keep the earlier record understandable.
A recorded signature, message or approval has context. Preserve the description that the customer was responding to rather than keeping an isolated “yes”. Your agreement and normal approval process determine what you need before proceeding.
Trace the approved change into billing
Before invoicing, check whether the approved amount is included and whether any part has already been billed. For progress billing, review previous claims as well as the revised value. Approval of a change and payment of an invoice are separate events.
Axiom Blue supports contract variations, approval states and revised contract values. Test the change on a sample fixed-price job and inspect the billing result. This guide explains recordkeeping; it does not determine whether a particular contractual approval is legally sufficient.
Make it useful today
Print or keep a working copy.
Each resource includes a blank worksheet and an illustrative example. Open it to print, or download an HTML copy to keep. No signup needed.
Put it to work
Your practical checklist
- Check the original scope before adding a charge.
- Describe the change and its timing effect.
- Keep the approval connected to the description.
- Update the crew’s current instruction.
- Reconcile the variation with previous and proposed billing.